Forum: Reliability & Maintainability Questions and AnswersTopic: Reliability & Maintainability Questions and Answers
Topic Posted by: Reliability & Maintainability Forum
(src_forum@alionscience.com
)
Organization: System Reliability Center
Date Posted: Mon Aug 31 12:47:36 US/Eastern 1998
Original Message:
Posted by: Wayne
Date posted: Mon Feb 24 8:05:38 US/Eastern 2003
Subject: AMSAA model fail
Message: I have a query that is i have only 2 failures during my Reliability growth testing. I fit in into the AMSAA model and it fails the goodness of fit test. In this case can i represent the system reliability by it's Observed MTBF which is = total test duration/ total failures? If not are there a better alternative since i have only 2 data points.
Previous reply
Reply:
Subject: Reply on the above
Reply Posted by: Wayne
Date Posted: Tue Mar 11 21:24:15 US/Eastern 2003
Message: Thanks for your long reply. As far as planning is concern, the total test duration is derived based on the Duane Model reliability planning.We currently have only 1 prototype so the number of units is constraint in our case. We only realise that there are only 2 chargeable failures after completing the whole test duration.
In our case we could not stop at the 2nd or even 3rd failure, we have to complete the whole test duration. I thought it is suppose to be a time terminate test? Please advise!! Thanks
|